Bid evaluation

How to compare greenhouse quotations

Direct answer

Do not compare greenhouse quotations on price per square metre. Normalise each bid first: usable production area, structure type and stated wind and snow loads, covering specification, ventilation area, heating and cooling capacity at design conditions, screens, lighting, irrigation and fertigation, water treatment, growing system, controls, electrical and civil scope, freight and Incoterm, installation, commissioning, training, warranty, spare parts, expected annual energy and water consumption, programme, and written exclusions. Only after that adjustment is a price difference meaningful.

Two greenhouse offers for the same hectare figure can differ by a factor of two and both be honest. The gap is almost always in usable area, climate design conditions and what has been excluded rather than in margin.

Define the crop, climate and business model before choosing the greenhouse company.

Step 1 — restate every bid on the same production area

Gross covered area includes corridors, technical rooms and headland. Usable production area is what generates yield. Convert every bid to cost per usable square metre before any other comparison.

Step 2 — check the design conditions, not the equipment list

  • Which external temperature, humidity and radiation values was the climate system designed against?
  • Which wind speed and snow load standard was the structure designed to?
  • What internal set-points were assumed for the crop, and do they match your crop plan?
  • What water quality and source were assumed for irrigation and treatment?

Step 3 — build the exclusions column

List every item that appears in one bid and not another: foundations, site levelling, electrical connection, standby power, water source development, import duties, local permits, accommodation for installation crews, and post-handover service. Price the missing items from the other bids and add them back before comparing.

Step 4 — model operating cost, not just CAPEX

  • Stated annual energy consumption per square metre, and the tariff assumed
  • Water consumption and whether drain water is recirculated
  • Screen and covering replacement intervals
  • Labour implications of the automation level offered
  • Spare-parts availability and service response time in your country

Step 5 — score technical and commercial separately

Keep technical compliance and commercial terms in separate columns. A bid that is technically non-compliant should be clarified or excluded before price is considered, otherwise the cheapest non-compliant offer distorts the whole evaluation.

The normalisation checklist

Restate every bid against each line below before comparing price. A blank cell in any bid is an exclusion until the supplier confirms otherwise in writing.

GroupLines to normalise
Area and structureGross covered area vs usable production area · Structure type (Venlo, multi-span plastic, tunnel, semi-closed, retractable) · Gutter height and bay/span dimensions · Design wind load and snow load, and the standard applied · Glazing or covering specification and expected light transmission · Foundations and civil works scope
Climate systemsVentilation type, vent area as a percentage of floor area, and insect netting · Heating capacity, heat source and distribution · Cooling strategy (natural, pad-and-fan, fogging, semi-closed) and design conditions · Thermal and shade screens, number of layers and control · Supplemental lighting type, installed W/m² and photoperiod assumption · CO2 supply, if included
Water, irrigation and growing systemIrrigation and fertigation units, dosing channels and EC/pH control · Water treatment, filtration, disinfection and drain recirculation · Water storage, reservoirs and pump stations · Growing system — gutters, substrate, hydroponic troughs or soil · Sensors, climate computer and software licences
Commercial and deliveryElectrical scope, transformer, standby power and connection responsibility · Installation labour, supervision and local subcontracting split · Freight, Incoterm, packing and site unloading · Import duties, taxes and customs responsibility · Commissioning, performance testing and handover criteria · Training, documentation and spare-parts package · Warranty periods per system and service response terms · Delivery programme and milestone dates · Expected energy and water consumption per year · Written exclusions — the single most common cause of non-comparable bids

Questions buyers ask before selecting a greenhouse company

SeedMatch Group is not a greenhouse manufacturer, integrator, EPC contractor or installer, and has no exclusive relationship with any company named on this page. Several of the companies described here can be invited to quote through a structured RFQ. Capability descriptions summarise categories these companies present publicly and should be verified directly with each company for a specific project.

Greenhouse bid comparison tool

Enter two or three bids and see where they are not comparable.

Before you request greenhouse quotes

The pre-RFQ definition checklist that makes bids comparable.

Commercial greenhouse RFQ template

Section-by-section specification structure for a professional tender.

Hidden costs in greenhouse quotations

Twelve scope gaps that make the cheapest per m² the more expensive project.

Build a structured greenhouse RFQ

Turn crop, climate and production targets into one comparable scope sheet.

Greenhouse ROI / TCO calculator

Combine CAPEX, energy, water, labour and cycles into lifecycle cost.

Commercial greenhouse cost and CAPEX bands

Conditional cost ranges by structure, climate and technology level.

Turnkey greenhouse suppliers compared
Build a structured RFQ Configure the project first
Project-specific agronomy and engineering are provided by the selected qualified independent professionals and contractors. SeedMatch Group gathers requirements, structures the pre-RFQ brief and coordinates independent proposals; it does not design greenhouses, specify crop plans, select varieties or deliver construction.
SeedMatch Group is not a bank, lender, financing institution, credit provider or investment adviser. It may help eligible project sponsors prepare information and submit requests to independent financing providers. All eligibility, due diligence, credit decisions, pricing, security, terms and disbursement are controlled solely by those providers.
Next step

Turn this into a live commercial project

Open one private brief and a dedicated sourcing specialist returns normalised, side-by-side quotations from qualified international suppliers — with equipment, CAPEX and project-finance routes mapped alongside.

FinancingStart Procurement