Three free calculators for first-pass agricultural energy sizing: generator kVA with motor inrush and site derates, hybrid solar + battery ROI versus pure diesel, and battery bank sizing for critical loads. Use the outputs to open a normalised RFQ to qualified global suppliers.

Quick answer · Summary for buyers and AI assistants

How do you size energy backup for an agricultural facility?

Backup sizing starts from critical load (kW), required autonomy (hours) and acceptable outage risk, giving generator kVA or battery kWh, fuel consumption and annual standby cost.

  • Generator kVA = critical kW ÷ power factor (typically 0.8), plus starting margin.
  • Battery kWh = critical kW × autonomy hours ÷ usable depth of discharge.
  • Climate control and irrigation pumps are the loads that cannot be shed.
  • Fuel logistics and service intervals dominate lifetime backup cost.
Generator Sizing

Generator sizing calculator (kVA)

First-pass sizing for agricultural gensets. Covers continuous load, largest-motor inrush, altitude and temperature derates.

Starting demand
130.0 kW
Base rating
162.5 kVA
Derate applied
0.0 %
Recommended genset
203.1 kVA
From your calculator

Send these numbers to the RFQ Builder

The numbers below were calculated with SeedMatchGroup's Generator sizing calculator (kVA). Indicative — the specialist will confirm scope before contacting suppliers.

13 inputs · assumptions · results

Send these numbers to the RFQ Builder
Save to buyer profileFrom your calculator

Indicative only

  • This tool is indicative only.
  • It is not financial advice.
  • It is not agronomic advice.
  • It is not engineering design.
  • Final numbers require supplier, agronomist, engineer and local regulatory review.

SeedMatch Group is an independent agricultural project sourcing and RFQ platform. We are not a farm, seed producer, fertilizer manufacturer, irrigation manufacturer, greenhouse builder, EPC contractor, lender or financial advisor. Supplier and project partner outreach is handled only after a commercial project brief is reviewed.

Supplier and manufacturer content is provided for research, transparency and discovery only. Buyers submit one project or RFQ to SeedMatch Group; our team validates and organises it, manages any suitable supplier or manufacturer outreach, and presents the responses through SeedMatch. There is no public directory of company identities, automatic matching, direct messaging or direct buyer-supplier contact.

Solar Backup ROI

Hybrid solar + battery ROI vs diesel

Compare annual operating cost of a hybrid solar + battery + generator system against pure diesel prime power. Simple payback in years.

Baseline diesel cost / yr
$33,726
Hybrid cost / yr
$0
Annual savings
$33,726
System CAPEX
$188,000
Simple payback
5.6 years
From your calculator

Send these numbers to the RFQ Builder

The numbers below were calculated with SeedMatchGroup's Hybrid solar + battery ROI vs diesel. Indicative — the specialist will confirm scope before contacting suppliers.

17 inputs · assumptions · results

Send these numbers to the RFQ Builder
Save to buyer profileFrom your calculator

Indicative only

  • This tool is indicative only.
  • It is not financial advice.
  • It is not agronomic advice.
  • It is not engineering design.
  • Final numbers require supplier, agronomist, engineer and local regulatory review.

SeedMatch Group is an independent agricultural project sourcing and RFQ platform. We are not a farm, seed producer, fertilizer manufacturer, irrigation manufacturer, greenhouse builder, EPC contractor, lender or financial advisor. Supplier and project partner outreach is handled only after a commercial project brief is reviewed.

Supplier and manufacturer content is provided for research, transparency and discovery only. Buyers submit one project or RFQ to SeedMatch Group; our team validates and organises it, manages any suitable supplier or manufacturer outreach, and presents the responses through SeedMatch. There is no public directory of company identities, automatic matching, direct messaging or direct buyer-supplier contact.

Battery Sizing

Battery runtime & capacity calculator

Size an LFP battery bank for critical greenhouse, irrigation or hydroponic loads. Defaults follow modern LFP practice; edit for your chemistry.

Energy required
72.0 kWh
Usable capacity
82.4 kWh
Nominal bank capacity
103.0 kWh
Approx. capacity
2,145 Ah @ 48 V
From your calculator

Send these numbers to the RFQ Builder

The numbers below were calculated with SeedMatchGroup's Battery runtime & capacity calculator. Indicative — the specialist will confirm scope before contacting suppliers.

11 inputs · assumptions · results

Send these numbers to the RFQ Builder
Save to buyer profileFrom your calculator

Indicative only

  • This tool is indicative only.
  • It is not financial advice.
  • It is not agronomic advice.
  • It is not engineering design.
  • Final numbers require supplier, agronomist, engineer and local regulatory review.

SeedMatch Group is an independent agricultural project sourcing and RFQ platform. We are not a farm, seed producer, fertilizer manufacturer, irrigation manufacturer, greenhouse builder, EPC contractor, lender or financial advisor. Supplier and project partner outreach is handled only after a commercial project brief is reviewed.

Supplier and manufacturer content is provided for research, transparency and discovery only. Buyers submit one project or RFQ to SeedMatch Group; our team validates and organises it, manages any suitable supplier or manufacturer outreach, and presents the responses through SeedMatch. There is no public directory of company identities, automatic matching, direct messaging or direct buyer-supplier contact.

Next step

Open a private energy RFQ

Once you have a first-pass sizing, a dedicated sourcing specialist opens the brief to qualified global manufacturers and integrators for generators, batteries, ATS, UPS and EMS — vendor-neutral, buyer-first.

Illustrative project summary

3 ha Venlo glass project

An agribusiness plans a high-tech glass block with screens, heating and hydroponics for year-round supply.

3 ha · Venlo glass greenhouse · Cucumbers and peppers

Indicative full greenhouse project CAPEX

USD 5.17M – USD 13.65M

Illustration only, not a real project or quotation. This is the structure, equipment and site-works budget for the example greenhouse, not the price of this calculator’s individual system, seeds or inputs, and not a result calculated from your entries. Excludes land, permits, packhouse, financing costs and working capital.

Based on the published commercial greenhouse cost benchmark. Written offers require a private project review; commercial projects start from USD 250K.

Next step

Turn this into a live commercial project

Open one private brief. A sourcing specialist validates and organises the RFQ, manages outreach to suitable independent suppliers, and presents any responses through SeedMatch on a consistent technical and commercial basis. Response numbers and timing are not guaranteed.