Factory Acceptance Testing (FAT) for Agricultural and Seed-Processing Equipment

Factory Acceptance Testing is the last realistic chance to catch a defect before equipment leaves the manufacturer. For any capital purchase above USD 100,000 — seed-processing lines, sorting graders, greenhouse climate systems, irrigation head-stations — a documented FAT should be a contract condition and a payment milestone.

Direct answer

Can FAT be done remotely?

Yes — many suppliers now offer video-witnessed FAT with a signed report. It is acceptable for lower-value orders but on-site FAT remains the standard above USD 250,000. The supplier hosts and pays for the test itself. The buyer pays for their own travel and any third-party inspector.

Skip the reading

Paste your brief straight into our RFQ Builder — we identify qualified independent global suppliers on your behalf. Free for buyers.

Open the RFQ Builder

When FAT is essential

FAT is standard practice for seed-processing plants, packing houses, cold rooms, irrigation head-stations, greenhouse climate controllers and any custom-fabricated equipment. It is usually skipped for off-the-shelf items under USD 50,000.

What a professional FAT protocol contains

The FAT document is agreed in writing at contract signature, not at test time:

  • Scope: exact equipment, model numbers, serial numbers.
  • Test conditions: input material, throughput, ambient conditions.
  • Pass / fail criteria for each test (accuracy, throughput, energy, uniformity).
  • Attendees: buyer, supplier, third-party inspector if used.
  • Documentation: signed test record, deviation list, corrective actions.
  • Consequences: what happens if the equipment fails (rework, discount, cancellation).

Third-party inspection

For orders above USD 250,000, budget 0.3–0.7% of contract value for an independent inspector (SGS, Bureau Veritas, TÜV). Their signed report is what banks and insurers rely on.

FAT as a payment milestone

Standard payment structure for capital equipment: 30% at contract, 60% at successful FAT, 10% at successful SAT. Never release the pre-shipment tranche before FAT is signed.

Frequently asked questions

Ready to send a real RFQ?

Our sourcing specialist identifies qualified independent seed producers across Africa, MENA, Europe, Asia and the Americas, requests offers on your behalf and returns a side-by-side comparison. Private by default, free for buyers.

Start your RFQ
Related calculators, country guides & pre-filled RFQ

Curated calculators, country buying guides and a pre-filled RFQ so you can move from research to a comparable-offer brief in one step.

Next step

Turn this into a live commercial project

Open one private brief and a dedicated sourcing specialist returns normalised, side-by-side quotations from qualified international suppliers — with equipment, CAPEX and project-finance routes mapped alongside.

FinancingStart Procurement