Morocco greenhouse permits: issuing authorities and time limits
Which public bodies issue building licences and project approvals for commercial greenhouses in Morocco, and the time limits written into law for each decision.
Who issues the permits
- Regional Investment Centre (CRI) — Single point of contact for investment projects and related administrative approvals in each region.
- Agricultural Development Agency (ADA) — Supports agricultural investment under the Generation Green strategy.
Legal time limits in Morocco
Urban-planning information note (note de renseignements urbanistiques)
2 working days
Decree 2-18-577 (General Construction Regulation), art. 7Review committee minutes sent to the commune president for decision
3 working days after the meeting
Decree 2-18-577, art. 38Decision notified to the applicant
2 working days after the decision
Decree 2-18-577, arts. 43–44
The decree sets deadlines for each stage, not one overall figure for a building permit.
These are the limits written into law. Real processing times can be longer.
Public bodies and laws are named as institutional context; checklists are SeedMatchGroup planning guidance, not legal advice. Confirm current rules with the issuing authority.