Commercial greenhouse permits checklist by country
The approvals to line up before requesting supplier quotations, in order, for each market we cover. Public bodies, laws and time limits link to their public sources.
Steps that apply in every market
- Confirm the plot's land classification and that agricultural structures of your planned size are allowed.
- Identify which local and national bodies issue the building licence and any environmental review.
- Secure or confirm water rights (well, river or network supply) before sizing irrigation.
- Register the farm holding and plant-health obligations with the agriculture authority.
- Collect permit conditions (heights, setbacks, drainage) and attach them to your supplier RFQ.
Spain permit steps
- 1Municipal council (ayuntamiento): Urban-planning compatibility and building licence for greenhouse structures and auxiliary buildings.
- 2Autonomous community (comunidad autónoma): Regional land-use, environmental assessment and agricultural registration rules.
- 3Confirm the plot's land classification allows agricultural structures of the planned height and footprint.
- 4Check whether the project size triggers a regional environmental assessment before ordering steel.
- 5Register the holding and plant-health obligations with the regional agriculture department.
- 6Water — River basin authority (Confederación Hidrográfica): Grants water-use concessions and well authorisations under the consolidated Water Law. source
- 7Confirm an existing concession or irrigation-community allocation covers the planned volume before design.
- 8Test source salinity — it drives desalination or blending equipment in the RFQ.
Legal time limits
- Default maximum period for an administrative decision when no specific rule sets one: 3 months — Law 39/2015 on Common Administrative Procedure, art. 21.3
- Public notice period for competing applications after a concession request is published: 1 month — Public Hydraulic Domain Regulation (RD 849/1986), art. 105
- Applicant reply when the basin authority proposes limiting conditions: 15 days — Public Hydraulic Domain Regulation (RD 849/1986), art. 108
- Maximum length of a water-use concession: 75 years — Consolidated Water Law (RDL 1/2001), Title IV
Romania permit steps
- 1Local town hall: Issues the urbanism certificate (certificat de urbanism) and building permit (autorizație de construire) under Law 50/1991.
- 2AFIR — Agency for Financing Rural Investments: Manages EU rural-development investment calls relevant to protected horticulture. source
- 3Obtain the urbanism certificate first — it lists every approval the building permit will need.
- 4Check current AFIR call eligibility and timing before fixing the procurement schedule.
- 5Treat the Tomata de minimis scheme as operating support, not build financing.
- 6Water — Romanian Waters National Administration (Apele Române): Water-management permits and approvals for abstraction and discharge. source
- 7Confirm whether a water-management approval is required for the well or surface abstraction.
- 8Size storage for summer peaks and plan heating water/energy for winter production.
Legal time limits
- Urbanism certificate (certificat de urbanism): 15 working days from registration — Law 50/1991, art. 6(2) (as amended by Law 193/2019) — Portal Legislativ, Ministry of Justice
- Building permit (autorizație de construire): 30 days from a complete application — Law 50/1991, art. 7(1) — Portal Legislativ, Ministry of Justice
- Building permit for agricultural outbuildings on a farm: 15 days from registration — Law 50/1991, art. 7(1¹) — Portal Legislativ, Ministry of Justice
Morocco permit steps
- 1Regional Investment Centre (CRI): Single point of contact for investment projects and related administrative approvals in each region.
- 2Agricultural Development Agency (ADA): Supports agricultural investment under the Generation Green strategy.
- 3Confirm land tenure and whether the plot is privately titled, collective or state land before design.
- 4Check eligibility for agricultural investment incentives (Agricultural Development Fund) and the paperwork order they require.
- 5Water — Hydraulic basin agency (Agence du Bassin Hydraulique): Authorisations for wells and water abstraction under water law 36-15.
- 6Secure the abstraction authorisation before committing to crop area — water is often the binding constraint.
- 7Specify drip fertigation and water-use efficiency targets in every RFQ.
Legal time limits
- Urban-planning information note (note de renseignements urbanistiques): 2 working days — Decree 2-18-577 (General Construction Regulation), art. 7
- Review committee minutes sent to the commune president for decision: 3 working days after the meeting — Decree 2-18-577, art. 38
- Decision notified to the applicant: 2 working days after the decision — Decree 2-18-577, arts. 43–44
- River-basin agency review of an agricultural water-use authorisation: 60 days; no reply counts as approval — Water Law 36-15, art. 42
- Notice of refusal of an authorisation or concession: 15 days — Water Law 36-15, art. 38
- Completion of authorised desalination works: 4 years, with one extension of up to 2 years — Water Law 36-15, art. 76
Oman permit steps
- 1Ministry of Agriculture, Fisheries and Water Resources: Agricultural licensing, well permits and hydrometric data. source
- 2Ministry of Housing and Urban Planning: Land allocation and usufruct arrangements for agricultural plots.
- 3Confirm land usufruct or ownership terms and permitted agricultural use.
- 4Check import procedures and duty treatment for greenhouse equipment before setting delivery dates.
- 5Water — Ministry of Agriculture, Fisheries and Water Resources: Well technical specifications and water-resource permitting. source
- 6Scope water permits and source quality before equipment RFQs.
- 7Plan for desalination or reverse osmosis where groundwater salinity is high, and price its energy use.
Zambia permit steps
- 1Zambia Development Agency (ZDA): Investment registration and information on investor incentives. source
- 2Zambia Environmental Management Agency (ZEMA): Environmental assessment requirements for projects above set thresholds.
- 3Confirm land title or leasehold status and access roads before design.
- 4Check whether the project needs an environmental project brief or full assessment.
- 5Water — Water Resources Management Authority (WARMA): Water-use permits under the Water Resources Management Act, 2011. source
- 6Apply for the water-use permit for boreholes or surface abstraction early in planning.
- 7Plan backup power for pumps and climate equipment where grid supply is unreliable.
Cabo Verde permit steps
- 1Municipal chamber (câmara municipal): Local planning and construction licensing.
- 2Ministry of Agriculture and Environment: Agricultural policy and environmental requirements.
- 3Confirm land tenure and permitted use — arable land is limited.
- 4Check import procedures for equipment, since nearly all inputs arrive by sea.
- 5Water — National Water and Sanitation Agency (ANAS): National water-resource and sanitation regulator. source
- 6Water — Água de Rega (AdR): State company holding the national concession to manage and distribute irrigation water under Decree-Law 47/2021. source
- 7Confirm the irrigation water source and concession before sizing crop area.
- 8Price desalinated water or treatment if groundwater is limited or saline.
Public bodies and laws are named as institutional context; steps are SeedMatchGroup planning guidance, not legal advice. Confirm current rules with the issuing authority.