Romania greenhouse permits: issuing authorities and time limits

Which public bodies issue building licences and project approvals for commercial greenhouses in Romania, and the time limits written into law for each decision.

Who issues the permits

  • Local town hall — Issues the urbanism certificate (certificat de urbanism) and building permit (autorizație de construire) under Law 50/1991.
  • AFIR — Agency for Financing Rural Investments — Manages EU rural-development investment calls relevant to protected horticulture.

Legal time limits in Romania

  1. Urbanism certificate (certificat de urbanism)

    15 working days from registration

    Law 50/1991, art. 6(2) (as amended by Law 193/2019) — Portal Legislativ, Ministry of Justice
  2. Building permit (autorizație de construire)

    30 days from a complete application

    Law 50/1991, art. 7(1) — Portal Legislativ, Ministry of Justice
  3. Building permit for agricultural outbuildings on a farm

    15 days from registration

    Law 50/1991, art. 7(1¹) — Portal Legislativ, Ministry of Justice

These are the limits written into law. Real processing times can be longer.

Public bodies and laws are named as institutional context; checklists are SeedMatchGroup planning guidance, not legal advice. Confirm current rules with the issuing authority.

Next step

Turn this into a live commercial project

Open one private brief. A sourcing specialist validates and organises the RFQ, manages outreach to suitable independent suppliers, and presents any responses through SeedMatch on a consistent technical and commercial basis. Response numbers and timing are not guaranteed.