Commercial project planning

Project Planning Checklist: Land, Permits, Water, Construction & Costs

The execution-side checklist for commercial agricultural projects from USD 250,000 upwards. Work through five sections — land purchase, permits, water, construction readiness and cost planning — before committing capital or requesting supplier quotations. Print it or save it as PDF from your browser.

Start a private project brief
Section 1

Land purchase and site due diligence

A good price or location does not prove the land can carry the project. Verify title, permitted use, water, access and buildability with independent local professionals before purchase — not after.

  • Ownership, liens, easements and boundaries verified by independent local counsel
  • Agricultural and greenhouse use confirmed as permitted on the parcel
  • Zoning and development rights for the planned structures confirmed in writing
  • Net buildable area surveyed — excluding roads, buffers, reservoirs and slopesGross hectares overstate usable area
  • Geotechnical and drainage conditions assessed for foundations and floor loads
  • Flood, wind and climate exposure mapped against the structural specification
  • Road access and logistics route to the nearest port or market confirmed
  • Power connection point, capacity and upgrade responsibility identified
  • Purchase contract conditional on essential approvals, water and utilities
Section 2

Permits and approvals

Approval paths differ by country and by parcel. Map every permit — planning, environmental, construction, water abstraction, operating — with the responsible authority before closing on land or signing equipment contracts.

  • Full approval map drafted: planning, environmental, construction, water, operating
  • Responsible authority named for each approval, with statutory time limits where they exist
  • Environmental impact assessment requirement confirmed or ruled out
  • Building permit scope covers all planned structures, reservoirs and packhouse
  • Water abstraction or connection permit path confirmed with the water authority
  • Import, customs and phytosanitary requirements identified for equipment and seed
  • Operating licences and food-safety registrations listed for the target market
  • Approval sequence checked — which permits are prerequisites for others
Section 3

Water access and quality

Water quantity and quality stop more projects than structure choice. Lawful access, sustainable flow and a laboratory analysis must exist before irrigation, fertigation or treatment equipment can be specified.

  • Lawful water source confirmed: well, surface, municipal, desalinated or treated wastewater
  • Sustainable flow rate at peak demand measured, not estimated
  • Full laboratory analysis: EC, pH, sodium, chloride, bicarbonate, iron, boron, pathogens
  • Peak-day and seasonal demand calculated for the planned area and crop
  • Storage volume sized for peak-day buffer and supply interruptions
  • Treatment or blending requirement determined from the analysis
  • Drainage and discharge route confirmed, including recirculation rules where they apply
  • Backup source or emergency supply plan documented
Section 4

Construction readiness

Construction overruns usually come from scope gaps decided too late: civil works, foundations, power, water connections and commissioning responsibilities. Close them before signing any supply contract.

  • Scope boundary written down: what the supplier builds versus local civil works
  • Foundations, floors, roads and drainage costed separately from the structure
  • Power connection, transformer and backup power responsibilities assigned
  • Water connection, storage and treatment civils included in the works plan
  • Customs clearance, inland transport and site storage planned for imported equipment
  • Installation supervision, commissioning and acceptance testing defined in the contract
  • Construction schedule phased against crop calendar and financing drawdowns
  • Local contractor availability and capability verified for civil works
Section 5

Cost planning and financing

CAPEX alone never tells you whether a project works. Land, enabling works, equipment, installation, operating cost and financing structure must stand up together — including the downside scenario.

  • CAPEX split into land, enabling works, structure, systems, installation and contingency
  • Escalation and currency exposure allowed for on imported equipment
  • Annual OPEX modelled: energy, water, labour, inputs, maintenance, packaging, logistics
  • Cost per usable square metre and per kilo of saleable output calculated
  • Payback and ROI tested with a downside yield and price scenario
  • Working capital for the first production cycle included, not just build cost
  • Financing route chosen — equity, leasing or credit — with lender requirements listed
  • Budget figures treated as planning benchmarks, not supplier quotations

Where SeedMatchGroup fits

SeedMatchGroup is an independent, human-led commercial agriculture procurement platform. It does not manufacture, engineer, build, install, lend or guarantee outcomes, and it does not replace local lawyers, surveyors, agronomists or engineers. Once your planning is complete, a sourcing specialist helps structure the requirement and route a normalised RFQ to relevant manufacturers — suppliers contract and invoice you directly.

Questions about this checklist

Before committing capital to land or requesting supplier quotations. It covers the project-execution side — land, permits, water, construction and costs — that sits between early crop planning and the supplier RFQ.

The agricultural planning checklist captures agronomy inputs — crop, soil, climate, irrigation. This checklist covers the execution side: buying the land, securing permits, proving water access, preparing construction and structuring the budget.

No. Title, zoning, water rights and permits must be verified by independent local lawyers, surveyors, engineers and authorities. The checklist tells you what to ask them for, not how to replace them.

Commercial agricultural projects from USD 250,000 upwards. The same checks apply to smaller projects, but the depth is written for commercial investment scale.

Next step

Turn this into a live commercial project

Open one private brief. A sourcing specialist validates and organises the RFQ, manages outreach to suitable independent suppliers, and presents any responses through SeedMatch on a consistent technical and commercial basis. Response numbers and timing are not guaranteed.